Safe Streets for All

Safe Streets and Roads for All Grants

Forward to Vision Zero

Forward to Vision Zero cover for Federal Grant application to receive funding for Vision Zero Madison roadway safety projects.

The City’s two Safe Streets and Roads for All grants directly support Madison’s Vision Zero initiative to eliminate serous and fatal crashes by 2035. The first grant award focuses on additional planning to support our Vision Zero Action Plan. The second grant includes infrastructure improvements, demonstration activities and additional planning efforts. 

Forward to Vision Zero - Supplemental Action Plan Activities

The City’s first Safe Streets for All grant focuses on undertaking additional planning work to improve safety for people walking and biking. There is also funding to better understand how to improve post-crash care and integrate it with Vision Zero.

Update to Pedestrian Plan & Project Prioritization

Project Scope

  • Data Analysis
  • Community Engagement
  • Program & Policy Recommendations
  • Infrastructure Improvement Recommendations & Prioritization
  • Bike Pedestrian Focused High Injury Network

Project Manager

Kevin Luecke, Pedestrian Bicycle Administrator

Project Timeline

Plan completion Fall of 2026

Project Website

Pedestrian Plan website

Finalize All Ages Ability Bike Network Map & Project Prioritization

Project Scope

  • Data Analysis
  • Community Engagement
  • Finalize All Ages Ability Bike Network
  • Prioritize Gaps in the Network

Project Manager

Kevin Luecke, Pedestrian Bicycle Administrator

Project Timeline

Started; Plan completion Fall of 2026

Project Website

Bicycle Plan website

Safe Routes to School Travel Safety Planning

Project Scope

  • Work with up to 6 schools on:
    • School engagement
    • School walk/bike audits
    • Develop final school travel safety plans to share with school community

Project Manager

Colleen Hayes, Pedestrian Bicycle Outreach Specialist

Project Timeline

Safe Streets for All grant completed Fall of 2026

Project Website

Safe Routes to School website

Post Crash Care Data Review

Project Scope

  • Conduct a review of data to understand better understand the needs of EMS, Fire and Police to improve response times.
  • Integrate recommendations into Vision Zero Action Plan

Project Manager

TBD

Project Partner

UW Traffic Operations and Safety (TOPS) Laboratory

Project Timeline

Starting in Summer 2025

Project Website

Coming Soon

Forward to Vision Zero – Safe System for Vulnerable Roadway Users

The City’s 2nd Safe Streets for All grant awarded $6.3 million for infrastructure improvements, impaired driving countermeasures, safety studies, demonstration projects and additional safety focused planning. 

Regent Street

Project Scope Phase One

  • Data Collection & Analysis
  • Development of alternatives
  • Demonstration Project & Evaluation
  • Engagement
  • Final Corridor Study Report & Design Recommendation

Project Manager

Phase One: Tom Mohr, Assistant Director Mobility & Infrastructure

Project Timeline

Phase One: Start Summer 2025

Project Scope Phase Two

  • Surveying
  • Engineering Design Documents

Project Manager

Phase Two: Chris Petykowski, Deputy Director Engineering

Project Timeline

Phase Two: TBD

Project Website

Coming Summer 2026

Supplemental Planning

High Injury Network (HIN) Update & Crash Risk Analysis

Project Manager

Ali Heinritz, Vision Zero Co-Lead

Project Timeline

Summer 2026

Project Website

High Injury Network webpage


 Vision Zero Progress Report

Project Manager

Vision Zero Steering Team, Staff

Project Timeline

Continue regular progress report development for 2025-2026

Project Website

Vision Zero website


Let's Talk Streets Engagement Plan 

Project Manager

Liz Callin, Transportation Planner

Project Timeline

Summer 2026

Project Website

Let's Talk Streets webpage

Corridor Safety Studies & Demonstration Projects

Project Scope

  • Safety and Other Data Collection and Analysis
  • Demonstration Activities and Evaluation
  • Project Engagement
  • Development of design concepts

Locations

  • S Whitney Way
  • N Fair Oaks Ave
  • Schenk's Corners

Project Timeline

  • S Whitney Way – Tentative Start Date of Late 2025
  • N Fair Oaks Ave – Tentative Start Date of Fall 2026
  • Schenk’s Corners - Tentative Start Date of Spring 2027

Project Managers

Project Website

Coming Soon

Demonstration Activities

Asphalt Art Trial Project & Evaluation

Test & evaluate use of asphalt art on streets to determine safety benefit

Project Manager

Liz Callin, Transportation Planner

Resources

Bloomberg Philanthropies - Asphalt Art Safety Study

Timeline

Summer 2025

Asphalt Art project website


School Street Trial Project & Evaluation

Engage, implement & evaluate in partnership with MMSD and the Wisconsin Bike Fed Safe Routes to School program

Project Manager

Colleen Hayes, Pedestrian Bicycle Outreach Specialist

Resources

880 Cities – What is a School Street?

Timeline

spring 2026

School Street project website


65+ Bike & Pedestrian Friendly Driver Project

Work with older adults to develop & implement a project focused on building pedestrian and bicycle friendly 65+ year old drivers

Project Manager

Kristin Brodowsky, Public Information Officer

Proposed Outcome

  • Develop campaign with insight from focus groups
  • Evaluate the overall campaign success

Timeline

spring 2027 - On Hold

65+ Bike and Pedestrian Friendly Driver project website


Safe Mobility & Teen Crash Factors Demonstration Project

Work with high school age youth to develop & implement a public information campaign based on typical teen crashes

Project Manager 

Kristin Brodowsky, Public Information Officer

Proposed Outcome

  • Develop campaign with insight from focus groups
  • Evaluate the overall campaign success

Timeline

spring 2027 - On Hold

Safe Mobility and Teen Crash Factors website

Impaired Driving Reduction Initiative

Project Scope

  • Madison "safe ride" style program for local businesses and events
  • Compliance Checks

Project Manager

Julia Wilson, Impaired Driving Reduction Coordinator

Project Timeline

Summer 2025 - 2027

Project Website

Impaired Driving Reduction Program Website

Corridor Improvement Studies

East Washington Ave (US Hwy 30 to Annamark)

Project Scope

  • Fill gaps in sidewalk network
  • Bike Facility (Reindahl Park to E Springs Dr)
  • Lighting Improvements
  • Crosswalk Safety Enhancements

Project Manager

TBD

Project Timelines

  • Design & Engagement: 2027
  • Construction Start: 2028
  • Project Completion: Spring 2029

Project Website

Coming Soon


Schroeder Rd

Project Scope

  • Add Pedestrian Islands
  • Add Medians with Trees
  • Crosswalk Safety Enhancements
  • Transit Stop Improvements
  • Raised Crosswalk or Intersection

Project Manager

TBD

Project Timeline

  • Design & Engagement: 2027
  • Construction Start: 2028
  • Project Completion: Spring 2029

Project Website

Coming Soon

Systemwide Improvements

High Injury Network Intersections on Transit Routes

Project Scope

Proven Safety Countermeasures implemented at 21 intersections

Project Manager

Tom Mohr, Assistant Director Mobility & Infrastructure

Timeline

  • Design & Engagement: 2026
  • Construction Start: Fall 2027
  • Completion: Summer 2028

Project Website

Coming Soon


Shared-Use Path Intersections

Project Scope

Proven Safety Countermeasures

Locations:

  • Demetral Path Extension at E Johnson/Second
  • Capital City Path at Eastwood/Division
  • Capital City Path at Buckeye Rd
  • Southwest Path at Midvale Blvd
  • Eastmorland Park Path at Milwaukee St
  • Path at Aberg Ave and Shopko Dr

Project Manager

TBD

Project Timeline

  • Design & Engagement: 2026
  • Construction Start: Fall 2027
  • Completion: Summer 2028

Project Website

Coming Soon

Was this page helpful to you? * required