Olbrich Park Nature Play Area
Archived Project
This project is complete. This information is available for reference purposes.December 9, 2024 Update
Construction is now complete and the area is available for use. Parks crews will perform touch up work as necessary in the Spring.
View past project updates »Project Details
Project Information
Project Plan
The Parks Division maintains a replacement schedule for all of the city’s playgrounds and the playground at Olbrich Park near Lakeland Ave. was identified for removal this year. The typical lifespan of post and platform playground equipment is 20-30 years, and this playground has passed the standard expected lifespan. The playground was removed in early July 2023.
Parks has reviewed the location of the playground in the context of other playgrounds in the vicinity, and has decided to install a nature play area rather than a post and platform playground in this location. There are traditional post and platform playgrounds located nearby at Elmside Circle Park, Olbrich Park (Garrison St), and Olbrich Park (Walter St.). Nature play areas typically offer more open-ended play opportunities compared to conventional playgrounds. By providing natural materials and landscapes, children are encouraged to use their creativity and problem-solving skills to invent their own games and explore their surroundings. This approach fosters a sense of independence and self-directed learning, promoting cognitive and social development.
Public Input
Public Input Meeting #2
Monday, March 11, 2024 at 6:00pm via Zoom
Meeting Recording
Presentation Slides
Public Input Meeting #1
Tuesday, November 28, 2023 at 6:00pm via Zoom
Timeline
The Parks Division expects public engagement to be conducted in the winter of 2023-2024 and construction to occur in 2024.
Project Updates
December 9, 2024 Update
Construction is now complete and the area is available for use. Parks crews will perform touch up work as necessary in the Spring.
October 25, 2024 Update
The embankment slides have been installed. However, they will not be available for use for a few weeks while the concrete footings cure.
In the meantime, crews will begin installing the remaining features next week. There will be one adjustment to the project plan due to the soil types encountered. There will now be two boulder climbing features on the hillside, instead of one boulder feature and one wooden "steps" feature.
Additionally, the safety surfacing for the play area at the base of the slide will now be wood mulch, instead of pea gravel. After assessing site conditions, staff feels the wood mulch will do a better job of staying in place at the base of the slides.
October 16, 2024 Update
Parks has received the slides and plan to begin installation and the rest of the build-out on Monday, October 21.
August 15, 2024 Update
The swings have been installed and are ready for use. Parks crews will complete the remainder of the project after the embankment slides have been delivered.
July 12, 2024 Update
Parks is planning to start construction of the nature play area at Olbrich Park in the coming weeks. Next week (week of July 15) crews will be cutting existing vegetation to a height of 2-3 inches on the hillside in areas where the slides and climbing features will be installed. This is necessary in order to prepare for and install these features. Parks construction team will then begin work either late next week, or the week after (week of July 22).
The slides will be installed at a later date due to long lead times from the manufacturer. At this time, the delivery date of the slides is unknown. Some allowances during the initial phase of construction will be required to ensure equipment can access the slide locations for future installation.
June 26, 2024 Update
Parks intends to begin construction in mid-to-late July. The specific timeline is weather dependent on the Parks construction team completion of current projects which are in-progress.
The embankment slides will not be delivered in time for construction and will be installed at a later date after they are received from the manufacturer.
June 7, 2024 Update
Parks is working to procure the necessary products and materials for construction of the play area. Some products, particularly the slides, require custom manufacturing and extended manufacturing timeframes. Parks will identify a construction timeframe after the delivery dates of products is known.
March 25, 2024 Update
Parks has prepared a revised plan based on feedback from the second public meeting, held on March 11. If you have comments, please send them to akaniewski@cityofmadison.com by March 31.
View the Revised Plan
March 12, 2024 Update
Thank you to everyone who attended the second public meeting. The meeting recording and presentation slides have been added as links in the Public Input section below.
March 5, 2024 Update
A revised plan has been uploaded for viewing prior to the second public meeting, scheduled for March 11. Please see below to find the link to register in advance, and additional information.
February 12, 2024 Update
The second public meeting has been scheduled for March 11. Please see below to find the link to register in advance, and additional information.