Atwood Ave. Update - Nov. 13

posted 

This week, crews are installing the polymer overlay at the Starkweather Creek bridge. This work is expected to last the entire week and will require lane reductions in the area during operations and overnight. Please expect temporary traffic disruptions and delays while this work is being completed.

Atwood Avenue is currently open to bidirectional traffic from Fair Oaks Avenue to Cottage Grove Road. The multi-use path on the lakeside of Atwood Avenue is also open and access to all side streets has been restored.

Metro Transit has moved its inbound temporary bus stops to their permanent locations in the area. View more information on Metro Transit's website.

Crews have completed all concrete and asphalt recycling operations. There will be no more material recycling at the Garver site for the duration of the project.

WisDOT is the project lead for construction. Please email your comments and questions to ENComments@cityofmadison.com and we will work with the WisDOT construction engineer to provide answers.

View past project updates »