
Country Grove Park Shelter
Archived Project
This project is complete. This information is available for reference purposes.March 17, 2025 Update
The contractor will be working to complete work this spring. The shelter is available for reservations starting on June 6.
View past project updates »Project Details
Project Information
Parks identified a need for a park shelter building in this area of the city and have identified Country Grove Park as the location. The shelter building will include restrooms, a covered picnic area, and small parking lot. Additional information is available on the City of Madison Engineering Project Page.
Project Plans
A master planning process for Country Grove Park has identified a location for the shelter. The tentative project schedule is outlined below:
- Public Input and Design Development: Summer-Fall 2023
- Bidding and Contract Procurement: Winter 2024
- Construction Start: Spring 2024
- Construction Complete: Spring 2025
A contractor took soil borings in August 2023.
Project Updates
March 17, 2025 Update
The contractor will be working to complete work this spring. The shelter is available for reservations starting on June 6.
September 19, 2024 Update
The sanitary sewer and water lateral connections are complete. The contractor is continuing installation of the block masonry for the shelter and is also working to complete installation of the futsal/mini-pitch court.
September 6, 2024 Update
The contractor will be installing water and sanitary sewer utility connections during the week of September 9. The connections will require work within the East Pass right-of-way. Two-way traffic will be maintained during the duration of the work. However, the sidewalk on the east side of the road will be closed during this work.
The contractor has completed the building foundation and is currently installing the block masonry for the shelter.
The basketball and futsal court pavement has been completed. The basketball hoops and futsal court surround will be installed in the coming weeks.
July 12, 2024 Update
Construction is underway. Please stay out of the fenced work areas for the duration of the project.
June 20, 2024 Update
Recent rain has delayed the start of construction. Construction is anticipated to begin the week of 6/24.
May 14, 2024 Update
Construction is anticipated to begin on June 3rd. The basketball court will be closed during construction, as it is being removed and a new basketball and futsal court constructed to the west of the playground.
April 29, 2024 Update
The project received a successful bid and construction is anticipated to begin in May 2024.