Timeline

The  City of Madison antcipates the following tentative schedule of events for the RFP processes:

Milestone

Timing / Schedule

Release RFP

April 22, 2021

Pre-submittal info meeting

May 19, 2021

RFP due

July 19, 2021

RFP review and selection of preferred proposal

July 2021 – September 2021

BCC’s & Common Council approval to move forward with development agreement

October 2021 – December 2021

Determine project feasibility and negotiate development agreement

December 2021 – September 2022

BCC’s & Common Council approves development agreement

October 2022 – February 2023

Design/Construction Documents/City Entitlements

Q1 2022 – Q4 2024

Demolition/Construction begins

Q1 2025 – Q2 2025

 

Schedule is an estimate and subject to change.

Last Updated: 07/08/2021