The City of Madison antcipates the following tentative schedule of events for the RFP processes:
Milestone |
Timing / Schedule |
Release RFP |
April 22, 2021 |
Pre-submittal info meeting |
May 19, 2021 |
RFP due |
July 19, 2021 |
RFP review and selection of preferred proposal |
July 2021 – February 2022 |
Finance Committee review & recommendations |
March 2022 |
Council action on developer selection |
April 2022 |
Development Agreement negotiation |
May – December 2022 |
Council action on development agreement |
January - March 2023 |
Execution of development agreement |
March 2023 |
Design/Construction Documents/City Entitlements |
Q1 2024 - Q4 2024 |
Demolition/Construction start |
Q1 2025 - Q2 2025 |
Schedule is an estimate and subject to change.