Public Information Meeting: Elmside, Sommers, Center Reconstruction
postedOctober 20, 2025 Update
Public Involvement
There are a number of points of contact during this project where the public is encouraged to give feedback as part of public information meetings and public hearings. Dates, times and locations are indicated below: To Be Determined
Public Information Meetings
A public information meeting is scheduled for 6:30 p.m., Nov. 10, 2025, via Zoom. Registration prior is required.
Nov. 10, 2025 Public Information Meeting Registration
Please complete the project questionnaire by 1 p.m., Nov. 17, 2025.
Elmside Sommers Center Reconstruction Questionnaire(link is external)
City Process, Meetings
Common Council(link is external) February 10, 2026
Board of Public Works(link is external) January 28, 2026
Business Resources
City of Madison Business Resource Guide for Construction
Language Translation Services:
English:
A City of Madison Engineering project is planned in your area (Elmside Boulevard, Sommers Avenue, & Center Avenue Reconstruction). It may have an impact on you or your property. For language translation services, call 608-266-4751 in any language.
Spanish:
“El departamento de ingeniería de la ciudad de Madison tiene planeado un proyecto en su área. Este proyecto puede impactarlo a usted o a su propiedad. Para cualquier servicio de traducción en cualquier idioma, llame al 608-266-4751.
Project Details
Location
500 Elmside Blvd
Madison, WI 53704Project Type
Road ConstructionStatus
In DesignEstimated Schedule
June 16, 2026 – November 13, 2026Impact
MajorContract Number
8813
Project Information
Project Overview
The City is planning to reconstruct Elmside Blvd (Oakridge Ave to Atwood Ave), Sommers Ave (Miller Ave to Elmside Blvd, and Center Ave (Miller Ave to Elmside Blvd).
The project includes the replacement of sanitary sewer and laterals, water main, storm sewer main and laterals, curb and gutter, gravel base, asphalt pavement, and pavement marking. The sidewalk will be spot replaced as needed. The curb ramps will be replaced at the intersections to provide better access to pedestrians crossing the streets.
The project will also include connecting new sanitary sewer, water main, and storm sewer to existing facilities along Atwood Ave at Elmside Blvd as well as remove a portion of the asphalt pavement in the outside outbound lane (away from downtown) from Miller Avenue to Marquette St. Lane reductions are anticipated during construction.
Project Limits
Elmside Blvd – Oakridge Ave to Atwood Ave
Sommers Ave – Miller Ave to Elmside Blvd
Center Ave – Miller Ave to Maple Ave
Project Schedule
Design: Fall/Winter 2025/2026
Bids Advertised: Spring 2026
Construction: Summer – Fall 2026