Water Pipeline Rehabilitation Project - East

Project Details

Location

East Madison:
Woodvale Dr/Ferris Ave (from Acewood Ave to Eldorado Ln), Marg St, Meredithe Ave/Timothy Ave (from Acewood Ave to Eldorado Ln),
Madison, WI 53716

Status

Planning

Estimated Schedule

– October 2026

Impact

Minor

Alder District

  • District 16

East Madison:

Project Information

What is Cured-in-Place Pipe (CIPP)? 

Cured-in-Place Pipe, or CIPP, is a soft fabric linear installed inside the existing old pipe and is filled with epoxy resin. The fabric liner is inflated so it can fit tightly against the inside of the old pipe. It is then cured with hot water or steam to harden the liner. Once cured, it forms a new pipe inside the old water main. 

After the new pipe is in place, service connections are reopened from inside the pipe using robotic equipment. The finished water main is then pressure tested, disinfected, sampled, and tested before it is put back into service. 

The CIPP pipes will have full structural strength of a ductile iron pipe and are expected to last at least 50 years before additional maintenance needs to be considered. 

CIPP work being done
Image credit: Madison Water Utility

CIPP Project Overview

The streets of Ferris Ave, Woodvale Dr, Woodvale Cir, Marg St, Meredithe Ave, and Fleetwood Ave will be part of Madison Water Utility 2026 CIPP Project. These street segments were selected primarily because of their history of water main breaks.

The CIPP process allows a new pipe to be constructed inside of the existing old pipe, with minimal excavation in the street. The structural liner is designed to meet the physical strength properties of a new pipe. The contractor that is awarded for this project will be working on-site along with Madison Water Utility crews. This project helps improve water service, water quality, and fire protection.

During construction, street parking in the area will not be allowed. There will be short-term closures during off-peak traffic.

Temporary Water Service During Construction

During construction, the existing water main must be taken out of service. Customers directly affected by this work will receive water through a temporary above-ground drinking water system. The map below shows the homes that are expected to be connected to the temporary water system during construction. Customers connected to the temporary system will continue to receive drinking water while the existing water main is out of service.

The temporary water system will be disinfected, sampled, and tested using the same process used for new City of Madison water mains. Driveway and road crossings will be ramped up or buried so vehicles can still access homes and travel through the area.

Some affected properties may have their water meter removed during the project. The meter will be reinstalled after the water main work is complete.

The map below shows homes that will be connected to a temporary water system during construction, as the existing water main must be taken out of service. Customers will be provided water service through an above-ground, temporary drinking water system. The temporary system is disinfected, sampled and tested using the same procedures as all City of Madison water pipe installations.

Map of homes connected to temporary water system

Madison's History Using CIPP

Madison was the first city in Wisconsin to restore old water pipes using Cured-In-Place Pipe (CIPP) relining methods. The process allows Madison Water Utility (MWU) to create a new pipe inside an old water pipe without digging up the street for a full replacement. 

This will be Madison Water Utility's fourteenth year doing water pipeline rehabilitation contracts in this manner.  We have been working with and receiving assistance from WI Department of Natural Resources (DNR) over the years to develop, evaluate, and refine successful specifications for this technology.

Water Supply and Water Quality Benefits

Use of CIPP technology in the MWU water system meets the National Sanitation Foundation (NSF) Standard 61 for drinking water health and safety. This certification is required by the DNR to ensure water meets all standards set by the Environmental Protection Agency (EPA) Safe Drinking Water Act.

The liner, called Aquapipe®, is designed for water main rehabilitation and meets drinking water requirements. It forms a strong new pipe inside the old water main.

Licensed contractors have installed more than 600 miles of Aquapipe® in cities across North America, Australia, and Asia.

Using CIPP for this project will help reduce future water main breaks, improve water flow, and support water quality in the area. It also allows the work to be done at a lower cost than full water main replacement.

Frequently Asked Questions (FAQs)

Will I still have water service during construction?

Yes. Customers affected by the project will receive water through a temporary above-ground water system before the existing water main is taken out of service.

The temporary water system will be made from drinking water-safe materials (NSF 61). It will be disinfected, tested, and approved before it is used.

The temporary system is usually connected to the home through an outside hose connection. Some homes may have their water meter removed during the project and reinstalled after the work is complete.

When will construction take place?

Construction is expected to begin in June and finish in late September or early October.

The contractor may work during the following hours:

  • Monday through Saturday: 7:00 AM to 7:00 PM 
  • Sunday: 10:00 AM to 7:00 PM 

Will traffic be affected?

Roads will generally stay open, but some traffic may be restricted at times. There will be small excavation areas that are fenced and marked.

Temporary water pipes may be placed across driveways or roads. These crossings will be ramped up or buried to help maintain access.

Street parking will not be allowed in the project area during construction. Madison Metro Bus service is not expected to be affected.

Are there assessments or fees associated with this project?

There will be no assessments or residential fees associated with this project.

Why not install new water mains instead of rehabilitating the existing ones?

CIPP is often more cost effective than digging up and replacing the entire water main. It also reduces construction impacts because less excavation is needed.

This means less disruption for residents, a shorter construction schedule, and lower project costs.

Is CIPP as good as traditional pipe replacement materials?

Yes. The CIPP liner is designed to act as a new structural pipe inside the old pipe.

The liner must meet Wisconsin Department of Natural Resources requirements for new water mains. The design is prepared by a Professional Engineer and submitted to the DNR for review before construction begins.

The liner is designed to handle normal water system pressure and is expected to last at least 50 years.

What is involved in CIPP process?

Crews install a soft fabric liner inside the existing water main. The liner is filled with epoxy resin, then inflated so it fits tightly against the inside of the old pipe.

Heat is then used to harden the liner. Once it cures, it forms a new pipe inside the old water main.

After the new pipe is in place, service connections are reopened from inside the pipe using robotic equipment. The finished water main is then pressure tested, disinfected, sampled, and tested before it is put back into service.

Are CIPP systems safe for drinking water?

Yes. CIPP materials used in drinking water systems must meet NSF Standard 61. This standard helps make sure materials used in drinking water systems are safe.

The Wisconsin Department of Natural Resources requires this standard for drinking water projects.

Was this page helpful to you? * required