Jeffy Trail (Southern End to Raymond Rd.)
UPDATE (3/21/2017)
Jeffy Trail construction funds have been shifted to 2019. The City of Madison Planning Division is in the process of updating the High Point - Raymond Neighborhood Development Plan. More information about that process can be found at https://www.cityofmadison.com/dpced/planning/-high-point-raymond-neighborhood-development-plan/1823/
Details
This project involves the extension of Jeffy Trail from the existing south end to Raymond Rd., and this new street connection will provide improved access and connectivity for the neighborhood. The project will include installation of curb and gutter, new asphalt pavement, storm sewer and street lighting, and it will also include a pedestrian crossing of Jeffy Trail between the Jeffy Path and neighborhood sidewalk leading up to Trevor Way.
Schedule
Construction proposed 2019
Plan
plan
Public Informational Meetings
Meeting #1: September 23, 2015 at 7:00 PM at Olson Elementary School Cafeteria, 801 Redan Dr. Madison, WI
The presentation can be found here: presentation
The meeting handout can be found here: handout
An alternate plan discussed at the meeting can be found here: alt plan