PUBLIC WORKS CONTRACTS
CONTRACT NUMBER: 6781
CONTRACT: Eastwood Drive Sidewalk & Capital City Path Realignment
Percentage of Contract Completed:
96.0%
|
Associated Projects:
- Eastwood Drive Sidewalk & Capital City Path Realignment (53W1350)
|
PROJECT: |
Eastwood Drive Sidewalk & Capital City Path Realignment |
Project Number: |
53W1350 |
Bid Due Date: |
07/13/12
|
Bid Open Date: |
07/20/2012 |
Estimated Start Date: |
08/27/2012
|
Estimated Completion Date: |
09/30/2012
|
Percent of Project Completed: |
96.0 %
|
Contract Amount: |
$61,845.75
|
Project Contractor: |
RAYMOND P CATTELL INC
|
Construction Year: |
2012 |
Construction Type: |
Sidewalk |
District: |
06,
13,
|
PROJECT CONTACT: |
Project Manager: |
Eric Dundee |
Phone: |
608-266-4913 |
Email: |
edundee@cityofmadison.com |
Inspector: |
Ziegler-Henderson, Lauri |
Phone: |
261-5585 |
Documents & Specs
|