CONTRACT NUMBER: 6782
CONTRACT: Elderberry Road and Samuel Drive (new roads)
Percentage of Contract Completed:
100.4%
|
Associated Projects:
- Elderberry Road and Samuel Drive (new roads) (53W0977)
|
| PROJECT: |
Elderberry Road and Samuel Drive (new roads) |
| Project Number: |
53W0977 |
| Bid Due Date: |
12/28/12
|
| Bid Open Date: |
01/04/2013 |
| Estimated Start Date: |
04/29/2013
|
| Estimated Completion Date: |
07/19/2013
|
| Percent of Project Completed: |
100.4 %
|
| Contract Amount: |
$692,878.35
|
| Project Contractor: |
RG HUSTON COMPANY INC
|
| Construction Year: |
2013 |
| Construction Type: |
Street |
| District: |
09,
|
|
PROJECT CONTACT: |
| Project Manager: |
LeAnne Hannan |
| Phone: |
608-266-4057 |
| Email: |
lhannan@cityofmadison.com |
| Inspector: |
Mael, Stewart |
| Phone: |
261-9695 |