PUBLIC WORKS CONTRACTS
CONTRACT NUMBER: 6782
CONTRACT: Elderberry Road and Samuel Drive (new roads)
Percentage of Contract Completed:
100.4%
|
Associated Projects:
- Elderberry Road and Samuel Drive (new roads) (53W0977)
|
PROJECT: |
Elderberry Road and Samuel Drive (new roads) |
Project Number: |
53W0977 |
Bid Due Date: |
12/28/12
|
Bid Open Date: |
01/04/2013 |
Estimated Start Date: |
04/29/2013
|
Estimated Completion Date: |
07/19/2013
|
Percent of Project Completed: |
100.4 %
|
Contract Amount: |
$692,878.35
|
Project Contractor: |
RG HUSTON COMPANY INC
|
Construction Year: |
2013 |
Construction Type: |
Street |
District: |
09,
|
PROJECT CONTACT: |
Project Manager: |
LeAnne Hannan |
Phone: |
608-266-4057 |
Email: |
lhannan@cityofmadison.com |
Inspector: |
Mael, Stewart |
Phone: |
261-9695 |
Documents & Specs
|