CONTRACT NUMBER: 6792
CONTRACT: Midland Street Assessment District - 2012
Percentage of Contract Completed: 96.0%
Associated Projects:
  • Midland Street Reconstruction (53W1049)
PROJECT: Midland Street Reconstruction
Project Number: 53W1049
Bid Due Date: 06/08/12
Bid Open Date: 06/15/2012
Estimated Start Date: 08/15/2012
Estimated Completion Date: 09/30/2012
Percent of Project Completed: 96.0 %
Contract Amount: $252,560.30
Project Contractor: SPEEDWAY SAND & GRAVEL INC
Construction Year: 2012
Construction Type: Street
District: 13,
PROJECT CONTACT:
Project Manager: Jim Wolfe
Phone: 608-266-4099
Email: jwolfe@cityofmadison.com
Inspector: Ziegler-Henderson, Lauri
Phone: 261-5585