CONTRACT NUMBER: 6793
CONTRACT: N. Orchard St and Spring St Reconstruction Assessment District - 2012
Percentage of Contract Completed: 88.8%
Associated Projects:
  • N. Orchard St and Spring St Reconstruction (53W0608)
PROJECT: N. Orchard St and Spring St Reconstruction
Project Number: 53W0608
Bid Due Date: 01/27/12
Bid Open Date: 02/03/2012
Estimated Start Date: 05/29/2012
Estimated Completion Date: 08/10/2012
Percent of Project Completed: 88.8 %
Contract Amount: $1,210,792.00
Project Contractor: S & L UNDERGROUND & TRUCKING INC
Construction Year: 2012
Construction Type: Street
District: 08,
PROJECT CONTACT:
Project Manager: Glen Yoerger
Phone: 608-261-9177
Email: gyoerger@cityofmadison.com
Inspector: Hoel, Eric
Phone: