PUBLIC WORKS CONTRACTS
CONTRACT NUMBER: 6798
CONTRACT: RESURFACING 2012 – CURB & GUTTER AND CASTINGS WITH RESURFACING
Percentage of Contract Completed:
92.3%
|
Associated Projects:
- Resurfacing 2012 (53W1308)
|
PROJECT: |
Resurfacing 2012 |
Project Number: |
53W1308 |
Bid Due Date: |
01/27/12
|
Bid Open Date: |
02/03/2012 |
Estimated Start Date: |
04/02/2012
|
Estimated Completion Date: |
06/22/2012
|
Percent of Project Completed: |
92.3 %
|
Contract Amount: |
$309,398.50
|
Project Contractor: |
RAYMOND P CATTELL INC
|
Construction Year: |
2012 |
Construction Type: |
Street |
District: |
|
PROJECT CONTACT: |
Project Manager: |
John Fahrney |
Phone: |
608-266-9091 |
Email: |
jfahrney@cityofmadison.com |
Inspector: |
Armstrong, Steve |
Phone: |
266-4914 |
Documents & Specs
|