PUBLIC WORKS CONTRACTS
CONTRACT NUMBER: 6805
CONTRACT: Annual Horizontal Sawcutting of Concrete Sidewalk and Incidental Work
Percentage of Contract Completed:
91.9%
|
Associated Projects:
- Horizontal Sawcutting of Concrete Sidewalk and Incidental Work-2012 (53W1373)
|
PROJECT: |
Horizontal Sawcutting of Concrete Sidewalk and Incidental Work-2012 |
Project Number: |
53W1373 |
Bid Due Date: |
02/10/12
|
Bid Open Date: |
02/17/2012 |
Estimated Start Date: |
04/16/2012
|
Estimated Completion Date: |
12/31/2012
|
Percent of Project Completed: |
91.9 %
|
Contract Amount: |
$46,950.00
|
Project Contractor: |
SIDEWALK SAVERS LLC
|
Construction Year: |
2012 |
Construction Type: |
Sidewalk |
District: |
|
PROJECT CONTACT: |
Project Manager: |
Brenda Stanley |
Phone: |
608-266-4537 |
Email: |
bstanley@cityofmadison.com |
Inspector: |
Schlotthauer, Bill |
Phone: |
266-4088 |
Documents & Specs
|