PUBLIC WORKS CONTRACTS
CONTRACT NUMBER: 6829
CONTRACT: Forest Hill Cemetery Receiving Vault - Preservation of the North Wall
Percentage of Contract Completed:
99.3%
|
Associated Projects:
- Forest Hill Cemetery Receiving Vault - Preservation of the North Wall (53W1370)
|
PROJECT: |
Forest Hill Cemetery Receiving Vault - Preservation of the North Wall |
Project Number: |
53W1370 |
Bid Due Date: |
07/20/12
|
Bid Open Date: |
07/20/2012 |
Estimated Start Date: |
09/10/2012
|
Estimated Completion Date: |
11/08/2012
|
Percent of Project Completed: |
99.3 %
|
Contract Amount: |
$45,000.00
|
Project Contractor: |
B & B QUALITY BUILDING RESTORATION OF WISCONSIN INC
|
Construction Year: |
2012 |
Construction Type: |
Misc |
District: |
13,
|
PROJECT CONTACT: |
Project Manager: |
Paul Stauffer |
Phone: |
608-266-4366 |
Email: |
pstauffer@cityofmadison.com |
Inspector: |
Not Available |
Phone: |
Not Available |
Documents & Specs
|