CONTRACT NUMBER: 6835
CONTRACT: Kennedy Storm Bypass-Pipe-2012
Percentage of Contract Completed:
96.4%
|
Associated Projects:
- Kennedy Storm Bypass - Pipe - 2012 (53W1377)
|
| PROJECT: |
Kennedy Storm Bypass - Pipe - 2012 |
| Project Number: |
53W1377 |
| Bid Due Date: |
06/08/12
|
| Bid Open Date: |
06/15/2012 |
| Estimated Start Date: |
07/30/2012
|
| Estimated Completion Date: |
08/31/2012
|
| Percent of Project Completed: |
96.4 %
|
| Contract Amount: |
$112,864.00
|
| Project Contractor: |
HOMBURG CONTRACTORS INC
|
| Construction Year: |
2012 |
| Construction Type: |
Storm |
| District: |
03,
|
|
PROJECT CONTACT: |
| Project Manager: |
Max Conway |
| Phone: |
608-261-9127 |
| Email: |
mconway@cityofmadison.com |
| Inspector: |
Lauby, Paul |
| Phone: |
520-2378 |
Documents & Specs
|