CONTRACT NUMBER: 6882
CONTRACT: Utility Replacement with Resurfacing - 2012 (Regent Street)
Percentage of Contract Completed:
95.7%
|
Associated Projects:
- Regent Street Resurfacing with Utilities (53W1425)
|
PROJECT: |
Regent Street Resurfacing with Utilities |
Project Number: |
53W1425 |
Bid Due Date: |
04/06/12
|
Bid Open Date: |
04/13/2012 |
Estimated Start Date: |
05/22/2012
|
Estimated Completion Date: |
08/20/2012
|
Percent of Project Completed: |
95.7 %
|
Contract Amount: |
$1,857,075.13
|
Project Contractor: |
CAPITOL UNDERGROUND INC
|
Construction Year: |
2012 |
Construction Type: |
Street |
District: |
11,
|
PROJECT CONTACT: |
Project Manager: |
Eric Dundee |
Phone: |
608-266-4913 |
Email: |
edundee@cityofmadison.com |
Inspector: |
Mael, Stewart |
Phone: |
261-9695 |
Documents & Specs
|