PUBLIC WORKS CONTRACTS
CONTRACT NUMBER: 6950
CONTRACT: Boulevard/ROW Landscaping-2012
Percentage of Contract Completed:
100.0%
|
Associated Projects:
- Boulevard Landscaping-2012 (53W1473)
|
PROJECT: |
Boulevard Landscaping-2012 |
Project Number: |
53W1473 |
Bid Due Date: |
09/21/12
|
Bid Open Date: |
09/28/2013 |
Estimated Start Date: |
10/30/2012
|
Estimated Completion Date: |
11/28/2012
|
Percent of Project Completed: |
100.0 %
|
Contract Amount: |
$42,494.56
|
Project Contractor: |
DAN LARSEN LANDSCAPING
|
Construction Year: |
2012 |
Construction Type: |
Street |
District: |
|
PROJECT CONTACT: |
Project Manager: |
Glenn Clark |
Phone: |
608-266-4092 |
Email: |
gclark@cityofmadison.com |
Inspector: |
Clark, Glenn |
Phone: |
608-266-4092 |
Documents & Specs
|