PUBLIC WORKS CONTRACTS
CONTRACT NUMBER: 6969
CONTRACT: RESURFACING 2013 – ASPHALT BASE PATCHING AND BASE PATCH GRINDING
Percentage of Contract Completed:
87.9%
|
Associated Projects:
- Resurfacing 2013 (53W1492)
|
| PROJECT: |
Resurfacing 2013 |
| Project Number: |
53W1492 |
| Bid Due Date: |
01/25/13
|
| Bid Open Date: |
02/01/2013 |
| Estimated Start Date: |
05/21/2013
|
| Estimated Completion Date: |
11/15/2013
|
| Percent of Project Completed: |
87.9 %
|
| Contract Amount: |
$516,860.00
|
| Project Contractor: |
POBLOCKI PAVING CORP
|
| Construction Year: |
2013 |
| Construction Type: |
Street |
| District: |
|
|
PROJECT CONTACT: |
| Project Manager: |
John Fahrney |
| Phone: |
608-266-9091 |
| Email: |
jfahrney@cityofmadison.com |
| Inspector: |
McGlynn, Bill |
| Phone: |
266-4515 |
Documents & Specs
|