PUBLIC WORKS CONTRACTS
CONTRACT NUMBER: 6971
CONTRACT: RESURFACING 2013 - CURB & GUTTER AND CASTINGS WITH STORM SEWER
Percentage of Contract Completed:
92.6%
|
Associated Projects:
- Resurfacing 2013 (53W1492)
- Storm Sewer with Resurfacing 2013 (53W1522)
|
| PROJECT: |
Resurfacing 2013 |
| Project Number: |
53W1492 |
| Bid Due Date: |
03/22/13
|
| Bid Open Date: |
03/29/2013 |
| Estimated Start Date: |
05/27/2013
|
| Estimated Completion Date: |
08/09/2013
|
| Percent of Project Completed: |
92.6 %
|
| Contract Amount: |
$1,135,129.50
|
| Project Contractor: |
SPEEDWAY SAND & GRAVEL INC
|
| Construction Year: |
2013 |
| Construction Type: |
Street |
| District: |
|
|
PROJECT CONTACT: |
| Project Manager: |
John Fahrney |
| Phone: |
608-266-9091 |
| Email: |
jfahrney@cityofmadison.com |
| Inspector: |
Armstrong, Steve |
| Phone: |
266-4914 |
| PROJECT: |
Storm Sewer with Resurfacing 2013 |
| Project Number: |
53W1522 |
| Bid Due Date: |
03/22/13
|
| Bid Open Date: |
03/29/2013 |
| Estimated Start Date: |
05/27/2013
|
| Estimated Completion Date: |
08/09/2013
|
| Percent of Project Completed: |
92.6 %
|
| Contract Amount: |
$1,135,129.50
|
| Project Contractor: |
SPEEDWAY SAND & GRAVEL INC
|
| Construction Year: |
2013 |
| Construction Type: |
Storm |
| District: |
|
|
PROJECT CONTACT: |
| Project Manager: |
John Fahrney |
| Phone: |
608-266-9091 |
| Email: |
jfahrney@cityofmadison.com |
| Inspector: |
Armstrong, Steve |
| Phone: |
266-4914 |
Documents & Specs
|