PUBLIC WORKS CONTRACTS
CONTRACT NUMBER: 6985
CONTRACT: Warner Park Paths
Percentage of Contract Completed:
97.7%
|
Associated Projects:
- Warner Park Paths (53W1480)
|
PROJECT: |
Warner Park Paths |
Project Number: |
53W1480 |
Bid Due Date: |
05/24/13
|
Bid Open Date: |
05/31/2013 |
Estimated Start Date: |
09/10/2013
|
Estimated Completion Date: |
11/29/2013
|
Percent of Project Completed: |
97.7 %
|
Contract Amount: |
$844,562.65
|
Project Contractor: |
PARISI CONSTRUCTION CO INC
|
Construction Year: |
2013 |
Construction Type: |
Bike Path |
District: |
12,
18,
|
PROJECT CONTACT: |
Project Manager: |
Tony Fernandez |
Phone: |
608-266-9219 |
Email: |
afernandez@cityofmadison.com |
Inspector: |
Lauby, Paul |
Phone: |
|