CONTRACT NUMBER: 6987
CONTRACT: Merrill Crest Drive
Percentage of Contract Completed:
90.4%
|
Associated Projects:
- Merrill Crest Drive (53W1478)
|
| PROJECT: |
Merrill Crest Drive |
| Project Number: |
53W1478 |
| Bid Due Date: |
04/19/13
|
| Bid Open Date: |
04/19/2013 |
| Estimated Start Date: |
06/17/2013
|
| Estimated Completion Date: |
08/28/2013
|
| Percent of Project Completed: |
90.4 %
|
| Contract Amount: |
$589,514.80
|
| Project Contractor: |
S & L UNDERGROUND & TRUCKING INC
|
| Construction Year: |
2013 |
| Construction Type: |
Street |
| District: |
11,
|
|
PROJECT CONTACT: |
| Project Manager: |
LeAnne Hannan |
| Phone: |
608-266-4057 |
| Email: |
lhannan@cityofmadison.com |
| Inspector: |
Mael, Stewart |
| Phone: |
261-9695 |