PUBLIC WORKS CONTRACTS
CONTRACT NUMBER: 7000
CONTRACT: Repairing & Sealing Pavement Cracks, Local Streets - 2013
Percentage of Contract Completed:
87.4%
|
Associated Projects:
- Repairing & Sealing Pavement Cracks, Local Streets - 2013 (53W1490)
|
PROJECT: |
Repairing & Sealing Pavement Cracks, Local Streets - 2013 |
Project Number: |
53W1490 |
Bid Due Date: |
04/05/13
|
Bid Open Date: |
04/12/2013 |
Estimated Start Date: |
05/28/2013
|
Estimated Completion Date: |
Not Available
|
Percent of Project Completed: |
87.4 %
|
Contract Amount: |
$111,917.00
|
Project Contractor: |
FAHRNER ASPHALT SEALERS LLC
|
Construction Year: |
2013 |
Construction Type: |
Street |
District: |
|
PROJECT CONTACT: |
Project Manager: |
Steve Sonntag |
Phone: |
608-267-1997 |
Email: |
ssonntag@cityofmadison.com |
Inspector: |
Not Available |
Phone: |
Not Available |
Documents & Specs
|