PUBLIC WORKS CONTRACTS
CONTRACT NUMBER: 7002
CONTRACT: Stoughton Road/Voges Road Intersection
Percentage of Contract Completed:
98.0%
|
Associated Projects:
- Stoughton Road/Voges Road Intersection (53W1332)
|
| PROJECT: |
Stoughton Road/Voges Road Intersection |
| Project Number: |
53W1332 |
| Bid Due Date: |
05/09/14
|
| Bid Open Date: |
05/09/2014 |
| Estimated Start Date: |
09/09/2014
|
| Estimated Completion Date: |
09/30/2014
|
| Percent of Project Completed: |
98.0 %
|
| Contract Amount: |
$109,677.00
|
| Project Contractor: |
SPEEDWAY SAND & GRAVEL INC
|
| Construction Year: |
2014 |
| Construction Type: |
Street |
| District: |
16,
|
|
PROJECT CONTACT: |
| Project Manager: |
LeAnne Hannan |
| Phone: |
608-266-4057 |
| Email: |
lhannan@cityofmadison.com |
| Inspector: |
Hoel, Eric |
| Phone: |
|
Documents & Specs
|