PUBLIC WORKS CONTRACTS
CONTRACT NUMBER: 7011
CONTRACT: Webster Street Reconstruction
Percentage of Contract Completed:
93.9%
|
Associated Projects:
- Webster Street Reconstruction (53W1194)
|
PROJECT: |
Webster Street Reconstruction |
Project Number: |
53W1194 |
Bid Due Date: |
02/22/13
|
Bid Open Date: |
03/01/2013 |
Estimated Start Date: |
03/29/2013
|
Estimated Completion Date: |
07/05/2013
|
Percent of Project Completed: |
93.9 %
|
Contract Amount: |
$1,344,895.69
|
Project Contractor: |
CAPITOL UNDERGROUND INC
|
Construction Year: |
2013 |
Construction Type: |
Street |
District: |
04,
|
PROJECT CONTACT: |
Project Manager: |
Jim Wolfe |
Phone: |
608-266-4099 |
Email: |
jwolfe@cityofmadison.com |
Inspector: |
Ziegler-Henderson, Lauri |
Phone: |
261-5585 |
Documents & Specs
|