PUBLIC WORKS CONTRACTS
CONTRACT NUMBER: 7117
CONTRACT: Badger Rock Path
Percentage of Contract Completed:
99.9%
|
Associated Projects:
- Badger Rock Path (53W1579)
|
| PROJECT: |
Badger Rock Path |
| Project Number: |
53W1579 |
| Bid Due Date: |
06/21/13
|
| Bid Open Date: |
06/21/2013 |
| Estimated Start Date: |
09/03/2013
|
| Estimated Completion Date: |
09/19/2013
|
| Percent of Project Completed: |
99.9 %
|
| Contract Amount: |
$62,290.00
|
| Project Contractor: |
HOMBURG CONTRACTORS INC
|
| Construction Year: |
2013 |
| Construction Type: |
Bike Path |
| District: |
14,
|
|
PROJECT CONTACT: |
| Project Manager: |
LeAnne Hannan |
| Phone: |
608-266-4057 |
| Email: |
lhannan@cityofmadison.com |
| Inspector: |
Hoel, Eric |
| Phone: |
|