CONTRACT NUMBER: 7161
CONTRACT: Streets West, Cold Storage Roof Replacement
Percentage of Contract Completed:
100.0%
|
Associated Projects:
- Streets West, Cold Storage Roof Replacement (53W1567)
|
| PROJECT: |
Streets West, Cold Storage Roof Replacement |
| Project Number: |
53W1567 |
| Bid Due Date: |
07/26/13
|
| Bid Open Date: |
07/26/2013 |
| Estimated Start Date: |
09/23/2013
|
| Estimated Completion Date: |
Not Available
|
| Percent of Project Completed: |
100.0 %
|
| Contract Amount: |
$147,640.00
|
| Project Contractor: |
MALY ROOFING CO INC
|
| Construction Year: |
2013 |
| Construction Type: |
Facilities |
| District: |
14,
|
|
PROJECT CONTACT: |
| Project Manager: |
Paul Stauffer |
| Phone: |
608-266-4366 |
| Email: |
pstauffer@cityofmadison.com |
| Inspector: |
Not Available |
| Phone: |
Not Available |
Documents & Specs
|