CONTRACT NUMBER: 7234
CONTRACT: Commonwealth Avenue, Fox Avenue, Gregory Street and Keyes Avenue Reconstruction District - 2014
Percentage of Contract Completed:
96.5%
|
Associated Projects:
- Commonwealth/Fox/Gregory Reconstruction (53W0615)
|
PROJECT: |
Commonwealth/Fox/Gregory Reconstruction |
Project Number: |
53W0615 |
Bid Due Date: |
04/11/14
|
Bid Open Date: |
04/11/2014 |
Estimated Start Date: |
05/19/2014
|
Estimated Completion Date: |
10/17/2014
|
Percent of Project Completed: |
96.5 %
|
Contract Amount: |
$2,829,185.80
|
Project Contractor: |
CAPITOL UNDERGROUND INC
|
Construction Year: |
2014 |
Construction Type: |
Street |
District: |
05,
13,
|
PROJECT CONTACT: |
Project Manager: |
Lisa Coleman |
Phone: |
608-266-4093 |
Email: |
lcoleman@cityofmadison.com |
Inspector: |
Ziegler-Henderson, Lauri |
Phone: |
261-5585 |