PUBLIC WORKS CONTRACTS
CONTRACT NUMBER: 7247
CONTRACT: Adams Street Reconstruction
Percentage of Contract Completed:
96.7%
|
Associated Projects:
- Adams Street Reconstruction (53W1052)
|
| PROJECT: |
Adams Street Reconstruction |
| Project Number: |
53W1052 |
| Bid Due Date: |
04/11/14
|
| Bid Open Date: |
04/11/2014 |
| Estimated Start Date: |
06/12/2014
|
| Estimated Completion Date: |
08/30/2014
|
| Percent of Project Completed: |
96.7 %
|
| Contract Amount: |
$564,253.89
|
| Project Contractor: |
CAPITOL UNDERGROUND INC
|
| Construction Year: |
2014 |
| Construction Type: |
Street |
| District: |
13,
|
|
PROJECT CONTACT: |
| Project Manager: |
LeAnne Hannan |
| Phone: |
608-266-4057 |
| Email: |
lhannan@cityofmadison.com |
| Inspector: |
Ziegler-Henderson, Lauri |
| Phone: |
261-5585 |
Documents & Specs
|