PUBLIC WORKS CONTRACTS
CONTRACT NUMBER: 7254
CONTRACT: John Nolen Path Reconstruction
Percentage of Contract Completed:
86.0%
|
Associated Projects:
- John Nolen Path Reconstruction (53W1712)
|
| PROJECT: |
John Nolen Path Reconstruction |
| Project Number: |
53W1712 |
| Bid Due Date: |
09/26/14
|
| Bid Open Date: |
09/26/2014 |
| Estimated Start Date: |
05/04/2015
|
| Estimated Completion Date: |
06/05/2015
|
| Percent of Project Completed: |
86.0 %
|
| Contract Amount: |
$124,353.00
|
| Project Contractor: |
BADGERLAND EXCAVATING CORP
|
| Construction Year: |
2015 |
| Construction Type: |
Bike Path |
| District: |
04,
|
|
PROJECT CONTACT: |
| Project Manager: |
Tony Fernandez |
| Phone: |
608-266-9219 |
| Email: |
afernandez@cityofmadison.com |
| Inspector: |
Vandenheuvel, Adam |
| Phone: |
264-4126 |
Documents & Specs
|