PUBLIC WORKS CONTRACTS
CONTRACT NUMBER: 7264
CONTRACT: 2014 Park Division, Parking & Water Utility Landscaping
Percentage of Contract Completed:
Not Available
|
Associated Projects:
- 2014 Park Division, Parking & Water Utility Landscaping (53W1742)
|
| PROJECT: |
2014 Park Division, Parking & Water Utility Landscaping |
| Project Number: |
53W1742 |
| Bid Due Date: |
02/21/14
|
| Bid Open Date: |
02/21/2014 |
| Estimated Start Date: |
05/18/2014
|
| Estimated Completion Date: |
11/15/2015
|
| Percent of Project Completed: |
Not Available
|
| Contract Amount: |
$139,988.75
|
| Project Contractor: |
MICHAEL J. AMBLE DBA MADISON COM. LANDSC
|
| Construction Year: |
2013 |
| Construction Type: |
Misc |
| District: |
01,
02,
03,
05,
06,
09,
10,
11,
12,
16,
17,
18,
19,
|
|
PROJECT CONTACT: |
| Project Manager: |
Sarah Lerner |
| Phone: |
608-261-8592 |
| Email: |
slerner@cityofmadison.com |
| Inspector: |
Not Available |
| Phone: |
Not Available |
Documents & Specs
|