PUBLIC WORKS CONTRACTS
CONTRACT NUMBER: 7350
CONTRACT: Bowman Lighting System - Phase Two
Percentage of Contract Completed:
Not Available
|
Associated Projects:
- Bowman Lighting System - Phase Two (53W1815)
|
| PROJECT: |
Bowman Lighting System - Phase Two |
| Project Number: |
53W1815 |
| Bid Due Date: |
08/08/14
|
| Bid Open Date: |
08/08/2014 |
| Estimated Start Date: |
10/15/2014
|
| Estimated Completion Date: |
05/13/2015
|
| Percent of Project Completed: |
Not Available
|
| Contract Amount: |
$460,949.00
|
| Project Contractor: |
JOE DANIELS CONSTRUCTION CO INC
|
| Construction Year: |
2014 |
| Construction Type: |
Misc |
| District: |
14,
|
|
PROJECT CONTACT: |
| Project Manager: |
Michael Sturm |
| Phone: |
608-267-4921 |
| Email: |
mstrum@cityofmadison.com |
| Inspector: |
Not Available |
| Phone: |
Not Available |
Documents & Specs
|