                | PUBLIC WORKS CONTRACTS
				
				
			
						
						
						
							| CONTRACT NUMBER: 7351 CONTRACT: Wright Street Sidewalk
 Percentage of Contract Completed:
										101.1%
 |  
							| Associated Projects: 
									
										Sidewalk, Curb & Gutter, Citywide  Installation and Repair-2014 (53W1676) |  
						  
								
									 
									   | PROJECT: | Sidewalk, Curb & Gutter, Citywide  Installation and Repair-2014 |  
										| Project Number: | 53W1676 |  
										| Bid Due Date: | 06/27/14 |  
										| Bid Open Date: | 06/27/2014 |  
										| Estimated Start Date: | 09/18/2014 |  
										| Estimated Completion Date: | 09/29/2014 
 |  
										| Percent of Project Completed: | 101.1 % |  
										| Contract Amount: | $54,360.30 |  
										| Project Contractor: | S & L UNDERGROUND & TRUCKING INC |  
										| Construction Year: | 2014 |  
									  | Construction Type: | Sidewalk |  
									  | District: |  |  
										| PROJECT CONTACT: |  
									   | Project Manager: | Brenda Stanley |  
									   | Phone: | 608-266-4537 |  
									   | Email: | bstanley@cityofmadison.com |  
											| Inspector: | Lauby, Paul |  
											| Phone: | 520-2378 |  
							Documents & Specs				   |