PUBLIC WORKS CONTRACTS
CONTRACT NUMBER: 7351
CONTRACT: Wright Street Sidewalk
Percentage of Contract Completed:
101.1%
|
Associated Projects:
- Sidewalk, Curb & Gutter, Citywide Installation and Repair-2014 (53W1676)
|
PROJECT: |
Sidewalk, Curb & Gutter, Citywide Installation and Repair-2014 |
Project Number: |
53W1676 |
Bid Due Date: |
06/27/14
|
Bid Open Date: |
06/27/2014 |
Estimated Start Date: |
09/18/2014
|
Estimated Completion Date: |
09/29/2014
|
Percent of Project Completed: |
101.1 %
|
Contract Amount: |
$54,360.30
|
Project Contractor: |
S & L UNDERGROUND & TRUCKING INC
|
Construction Year: |
2014 |
Construction Type: |
Sidewalk |
District: |
|
PROJECT CONTACT: |
Project Manager: |
Brenda Stanley |
Phone: |
608-266-4537 |
Email: |
bstanley@cityofmadison.com |
Inspector: |
Lauby, Paul |
Phone: |
|
Documents & Specs
|