PUBLIC WORKS CONTRACTS
CONTRACT NUMBER: 7414
CONTRACT: RESURFACING 2015 – ASPHALT BASE PATCHING
Percentage of Contract Completed:
62.4%
|
Associated Projects:
- Resurfacing 2015 (53W1886)
|
PROJECT: |
Resurfacing 2015 |
Project Number: |
53W1886 |
Bid Due Date: |
02/20/15
|
Bid Open Date: |
02/20/2015 |
Estimated Start Date: |
06/09/2015
|
Estimated Completion Date: |
11/15/2015
|
Percent of Project Completed: |
62.4 %
|
Contract Amount: |
$977,798.00
|
Project Contractor: |
POBLOCKI PAVING CORP
|
Construction Year: |
2015 |
Construction Type: |
Street |
District: |
|
PROJECT CONTACT: |
Project Manager: |
John Fahrney |
Phone: |
608-266-9091 |
Email: |
jfahrney@cityofmadison.com |
Inspector: |
McGlynn, Bill |
Phone: |
266-4515 |