PUBLIC WORKS CONTRACTS
CONTRACT NUMBER: 7414
CONTRACT: RESURFACING 2015 – ASPHALT BASE PATCHING
Percentage of Contract Completed:
62.4%
|
Associated Projects:
- Resurfacing 2015 (53W1886)
|
| PROJECT: |
Resurfacing 2015 |
| Project Number: |
53W1886 |
| Bid Due Date: |
02/20/15
|
| Bid Open Date: |
02/20/2015 |
| Estimated Start Date: |
06/09/2015
|
| Estimated Completion Date: |
11/15/2015
|
| Percent of Project Completed: |
62.4 %
|
| Contract Amount: |
$977,798.00
|
| Project Contractor: |
POBLOCKI PAVING CORP
|
| Construction Year: |
2015 |
| Construction Type: |
Street |
| District: |
|
|
PROJECT CONTACT: |
| Project Manager: |
John Fahrney |
| Phone: |
608-266-9091 |
| Email: |
jfahrney@cityofmadison.com |
| Inspector: |
McGlynn, Bill |
| Phone: |
266-4515 |