CONTRACT: City Wide Street & Storm Upgrade and Repairs
Percentage of Contract Completed: 93.1%
Associated Projects:
  • City Wide Street & Storm Upgrade and Repairs (53W1898)
PROJECT: City Wide Street & Storm Upgrade and Repairs
Project Number: 53W1898
Bid Due Date: 02/06/15
Bid Open Date: 02/06/2015
Estimated Start Date: 04/13/2015
Estimated Completion Date: 05/29/2015
Percent of Project Completed: 93.1 %
Contract Amount: $221,566.14
Project Contractor: S & L UNDERGROUND & TRUCKING INC
Construction Year: 2015
Construction Type: Street
District: 09,
PROJECT CONTACT:
Project Manager: Glen Yoerger
Phone: 608-261-9177
Email: gyoerger@cityofmadison.com
Inspector: Mael, Stewart
Phone: 261-9695


Documents & Specs