CONTRACT NUMBER: 7423
CONTRACT: N Pinckney St Resurfacing w/Utilities
Percentage of Contract Completed: 98.5%
Associated Projects:
  • N Pinckney St Resurfacing w/Utilities (53W1846)
PROJECT: N Pinckney St Resurfacing w/Utilities
Project Number: 53W1846
Bid Due Date: 03/20/15
Bid Open Date: 03/20/2015
Estimated Start Date: 05/18/2015
Estimated Completion Date: 08/27/2015
Percent of Project Completed: 98.5 %
Contract Amount: $964,105.57
Project Contractor: S & L UNDERGROUND & TRUCKING INC
Construction Year: 2015
Construction Type: Street
District: 02,
PROJECT CONTACT:
Project Manager: Jim Wolfe
Phone: 608-266-4099
Email: jwolfe@cityofmadison.com
Inspector: Ziegler-Henderson, Lauri
Phone: 261-5585