CONTRACT NUMBER: 7424
CONTRACT: Chip Seal 2015-East
Percentage of Contract Completed:
95.1%
|
Associated Projects:
- Chip Seal 2015-East (53W1880)
|
| PROJECT: |
Chip Seal 2015-East |
| Project Number: |
53W1880 |
| Bid Due Date: |
03/06/15
|
| Bid Open Date: |
03/06/2015 |
| Estimated Start Date: |
04/27/2015
|
| Estimated Completion Date: |
Not Available
|
| Percent of Project Completed: |
95.1 %
|
| Contract Amount: |
$523,732.70
|
| Project Contractor: |
SCOTT CONSTRUCTION INC
|
| Construction Year: |
2015 |
| Construction Type: |
Street |
| District: |
|
|
PROJECT CONTACT: |
| Project Manager: |
Steve Sonntag |
| Phone: |
608-267-1997 |
| Email: |
ssonntag@cityofmadison.com |
| Inspector: |
Not Available |
| Phone: |
Not Available |