CONTRACT NUMBER: 7434
CONTRACT: Hanson Road
Percentage of Contract Completed:
106.1%
|
|
Associated Projects:
|
| PROJECT: |
Hanson Road |
| Project Number: |
53W1843 |
| Bid Due Date: |
03/27/15
|
| Bid Open Date: |
03/27/2015 |
| Estimated Start Date: |
05/18/2015
|
| Estimated Completion Date: |
06/01/2015
|
| Percent of Project Completed: |
106.1 %
|
| Contract Amount: |
$129,998.20
|
| Project Contractor: |
TRI COUNTY PAVING INC
|
| Construction Year: |
2015 |
| Construction Type: |
Street |
| District: |
17,
|
|
PROJECT CONTACT: |
| Project Manager: |
Steve Sonntag |
| Phone: |
608-267-1997 |
| Email: |
ssonntag@cityofmadison.com |
| Inspector: |
Armstrong, Steve |
| Phone: |
266-4914 |