PUBLIC WORKS CONTRACTS
CONTRACT NUMBER: 7451
CONTRACT: Center Ave and Sommers Ave Reconstruction
Percentage of Contract Completed:
91.6%
|
Associated Projects:
- Center Ave and Sommers Ave Reconstruction (53W1836)
|
| PROJECT: |
Center Ave and Sommers Ave Reconstruction |
| Project Number: |
53W1836 |
| Bid Due Date: |
04/10/15
|
| Bid Open Date: |
04/10/2015 |
| Estimated Start Date: |
05/18/2015
|
| Estimated Completion Date: |
07/17/2015
|
| Percent of Project Completed: |
91.6 %
|
| Contract Amount: |
$520,520.00
|
| Project Contractor: |
PARISI CONSTRUCTION CO INC
|
| Construction Year: |
2015 |
| Construction Type: |
Street |
| District: |
06,
|
|
PROJECT CONTACT: |
| Project Manager: |
LeAnne Hannan |
| Phone: |
608-266-4057 |
| Email: |
lhannan@cityofmadison.com |
| Inspector: |
Hoel, Eric |
| Phone: |
|
Documents & Specs
|