PUBLIC WORKS CONTRACTS
CONTRACT NUMBER: 7452
CONTRACT: Lakeview Reservoir Pipeline Improvements, Phase 2
Percentage of Contract Completed:
Not Available
|
Associated Projects:
- Lakeview Reservoir Pipeline Improvements, Phase 2 (53W1903)
|
PROJECT: |
Lakeview Reservoir Pipeline Improvements, Phase 2 |
Project Number: |
53W1903 |
Bid Due Date: |
04/07/17
|
Bid Open Date: |
04/07/2017 |
Estimated Start Date: |
05/29/2017
|
Estimated Completion Date: |
Not Available
|
Percent of Project Completed: |
Not Available
|
Contract Amount: |
$945,863.45
|
Project Contractor: |
SPEEDWAY SAND & GRAVEL INC
|
Construction Year: |
2017 |
Construction Type: |
Misc |
District: |
18,
|
PROJECT CONTACT: |
Project Manager: |
Kelly Miess |
Phone: |
261-9640 |
Email: |
kmiess@madisonwater.org |
Inspector: |
Not Available |
Phone: |
Not Available |
Documents & Specs
|