CONTRACT NUMBER: 7464
CONTRACT: Demetral Park Path
Percentage of Contract Completed:
90.8%
|
Associated Projects:
- Demetral Park Path (53W1911)
|
PROJECT: |
Demetral Park Path |
Project Number: |
53W1911 |
Bid Due Date: |
06/10/16
|
Bid Open Date: |
06/10/2016 |
Estimated Start Date: |
08/03/2016
|
Estimated Completion Date: |
11/01/2016
|
Percent of Project Completed: |
90.8 %
|
Contract Amount: |
$335,395.50
|
Project Contractor: |
RG HUSTON COMPANY INC
|
Construction Year: |
2016 |
Construction Type: |
Bike Path |
District: |
12,
|
PROJECT CONTACT: |
Project Manager: |
Chris Dawson |
Phone: |
261-5537 |
Email: |
cdawson@cityofmadison.com |
Inspector: |
Lauby, Paul |
Phone: |
|