PUBLIC WORKS CONTRACTS
CONTRACT NUMBER: 7557
CONTRACT: STREETS EAST STORMWATER IMPROVEMENT
Percentage of Contract Completed:
98.4%
|
Associated Projects:
- STREETS EAST STORMWATER IMPROVEMENT (53W1788)
|
| PROJECT: |
STREETS EAST STORMWATER IMPROVEMENT |
| Project Number: |
53W1788 |
| Bid Due Date: |
08/07/15
|
| Bid Open Date: |
08/07/2015 |
| Estimated Start Date: |
10/06/2015
|
| Estimated Completion Date: |
10/31/2015
|
| Percent of Project Completed: |
98.4 %
|
| Contract Amount: |
$158,927.15
|
| Project Contractor: |
SPEEDWAY SAND & GRAVEL INC
|
| Construction Year: |
2015 |
| Construction Type: |
Storm |
| District: |
17,
|
|
PROJECT CONTACT: |
| Project Manager: |
Lauren Striegl |
| Phone: |
608-266-4094 |
| Email: |
lstriegl@cityofmadison.com |
| Inspector: |
Lauby, Paul |
| Phone: |
520-2378 |
Documents & Specs
|