PUBLIC WORKS CONTRACTS
CONTRACT NUMBER: 7557
CONTRACT: STREETS EAST STORMWATER IMPROVEMENT
Percentage of Contract Completed:
98.4%
|
Associated Projects:
- STREETS EAST STORMWATER IMPROVEMENT (53W1788)
|
PROJECT: |
STREETS EAST STORMWATER IMPROVEMENT |
Project Number: |
53W1788 |
Bid Due Date: |
08/07/15
|
Bid Open Date: |
08/07/2015 |
Estimated Start Date: |
10/06/2015
|
Estimated Completion Date: |
10/31/2015
|
Percent of Project Completed: |
98.4 %
|
Contract Amount: |
$158,927.15
|
Project Contractor: |
SPEEDWAY SAND & GRAVEL INC
|
Construction Year: |
2015 |
Construction Type: |
Storm |
District: |
17,
|
PROJECT CONTACT: |
Project Manager: |
Lauren Striegl |
Phone: |
608-266-4094 |
Email: |
lstriegl@cityofmadison.com |
Inspector: |
Lauby, Paul |
Phone: |
|
Documents & Specs
|