CONTRACT NUMBER: 7558
CONTRACT: Felland Road Resurfacing
Percentage of Contract Completed: 92.8%
Associated Projects:
  • Felland Road Resurfacing (11176)
PROJECT: Felland Road Resurfacing
Project Number: 11176
Bid Due Date: 08/07/15
Bid Open Date: 08/07/2015
Estimated Start Date: 10/05/2015
Estimated Completion Date: 10/09/2015
Percent of Project Completed: 92.8 %
Contract Amount: $178,456.05
Project Contractor: TRI COUNTY PAVING INC
Construction Year: 2015
Construction Type: Street
District: 03,
PROJECT CONTACT:
Project Manager: Steve Sonntag
Phone: 608-267-1997
Email: ssonntag@cityofmadison.com
Inspector: Armstrong, Steve
Phone: 266-4914