PUBLIC WORKS CONTRACTS
CONTRACT NUMBER: 7623
CONTRACT: Capital Square Pavement Replacement Phase 1
Percentage of Contract Completed:
96.2%
|
Associated Projects:
- Capital Square Pavement Replacement Phase 1 (10903)
|
PROJECT: |
Capital Square Pavement Replacement Phase 1 |
Project Number: |
10903 |
Bid Due Date: |
02/19/16
|
Bid Open Date: |
02/19/2016 |
Estimated Start Date: |
03/28/2016
|
Estimated Completion Date: |
08/15/2016
|
Percent of Project Completed: |
96.2 %
|
Contract Amount: |
$2,128,316.70
|
Project Contractor: |
S & L UNDERGROUND & TRUCKING INC
|
Construction Year: |
2016 |
Construction Type: |
Street |
District: |
04,
|
PROJECT CONTACT: |
Project Manager: |
Jim Wolfe |
Phone: |
608-266-4099 |
Email: |
jwolfe@cityofmadison.com |
Inspector: |
Ziegler-Henderson, Lauri |
Phone: |
261-5585 |
Documents & Specs
|