PUBLIC WORKS CONTRACTS
CONTRACT NUMBER: 7625
CONTRACT: Cottage Grove Road Resurfacing
Percentage of Contract Completed:
95.6%
|
Associated Projects:
- Cottage Grove Road Resurfacing (11099)
|
PROJECT: |
Cottage Grove Road Resurfacing |
Project Number: |
11099 |
Bid Due Date: |
03/30/16
|
Bid Open Date: |
03/30/2016 |
Estimated Start Date: |
05/16/2016
|
Estimated Completion Date: |
08/19/2016
|
Percent of Project Completed: |
95.6 %
|
Contract Amount: |
$3,272,182.52
|
Project Contractor: |
SPEEDWAY SAND & GRAVEL INC
|
Construction Year: |
2016 |
Construction Type: |
Street |
District: |
03,
16,
|
PROJECT CONTACT: |
Project Manager: |
LeAnne Hannan |
Phone: |
608-266-4057 |
Email: |
lhannan@cityofmadison.com |
Inspector: |
Hoel, Eric |
Phone: |
|
Documents & Specs
|