PUBLIC WORKS CONTRACTS
CONTRACT NUMBER: 7626
CONTRACT: Fordem Aveune Utility Replacement w/Resurfacing
Percentage of Contract Completed:
98.4%
|
Associated Projects:
- Fordem Aveune Utility Replacement w/Resurfacing (11095)
|
| PROJECT: |
Fordem Aveune Utility Replacement w/Resurfacing |
| Project Number: |
11095 |
| Bid Due Date: |
04/27/16
|
| Bid Open Date: |
04/27/2016 |
| Estimated Start Date: |
06/06/2016
|
| Estimated Completion Date: |
10/31/2016
|
| Percent of Project Completed: |
98.4 %
|
| Contract Amount: |
$3,242,782.53
|
| Project Contractor: |
RG HUSTON COMPANY INC
|
| Construction Year: |
2016 |
| Construction Type: |
Street |
| District: |
02,
12,
|
|
PROJECT CONTACT: |
| Project Manager: |
Glen Yoerger |
| Phone: |
608-261-9177 |
| Email: |
gyoerger@cityofmadison.com |
| Inspector: |
Lauby, Paul |
| Phone: |
520-2378 |