CONTRACT NUMBER: 7643
CONTRACT: Bedford Street and MATC Pipe Bursting
Percentage of Contract Completed:
93.0%
|
Associated Projects:
- Bedford Street and MATC Pipe Bursting (11211)
|
| PROJECT: |
Bedford Street and MATC Pipe Bursting |
| Project Number: |
11211 |
| Bid Due Date: |
06/01/16
|
| Bid Open Date: |
06/01/2016 |
| Estimated Start Date: |
08/05/2016
|
| Estimated Completion Date: |
Not Available
|
| Percent of Project Completed: |
93.0 %
|
| Contract Amount: |
$189,582.75
|
| Project Contractor: |
SPEEDWAY SAND & GRAVEL INC
|
| Construction Year: |
2016 |
| Construction Type: |
Sanitary |
| District: |
04,
12,
|
|
PROJECT CONTACT: |
| Project Manager: |
Eric Dundee |
| Phone: |
608-266-4913 |
| Email: |
edundee@cityofmadison.com |
| Inspector: |
Ziegler-Henderson, Lauri |
| Phone: |
261-5585 |