PUBLIC WORKS CONTRACTS
CONTRACT NUMBER: 7666
CONTRACT: N. Segoe Road Water Main Replacement
Percentage of Contract Completed:
Not Available
|
Associated Projects:
- N. Segoe Road Water Main Replacement (11306)
|
PROJECT: |
N. Segoe Road Water Main Replacement |
Project Number: |
11306 |
Bid Due Date: |
06/10/16
|
Bid Open Date: |
06/10/2016 |
Estimated Start Date: |
08/08/2016
|
Estimated Completion Date: |
Not Available
|
Percent of Project Completed: |
Not Available
|
Contract Amount: |
$277,471.80
|
Project Contractor: |
SPEEDWAY SAND & GRAVEL INC
|
Construction Year: |
2016 |
Construction Type: |
Misc |
District: |
11,
|
PROJECT CONTACT: |
Project Manager: |
Pete Holmgren |
Phone: |
261-5530 |
Email: |
pholmgren@madisonwater.org |
Inspector: |
Not Available |
Phone: |
Not Available |
Documents & Specs
|