PUBLIC WORKS CONTRACTS
CONTRACT NUMBER: 7685
CONTRACT: Engineering Operations Building Addition
Percentage of Contract Completed:
100.0%
|
Associated Projects:
- Engineering Operations Building Addition (53W1386)
|
| PROJECT: |
Engineering Operations Building Addition |
| Project Number: |
53W1386 |
| Bid Due Date: |
03/09/16
|
| Bid Open Date: |
03/09/2016 |
| Estimated Start Date: |
04/25/2016
|
| Estimated Completion Date: |
Not Available
|
| Percent of Project Completed: |
100.0 %
|
| Contract Amount: |
$3,499,709.00
|
| Project Contractor: |
MIRON CONSTRUCTION CO INC
|
| Construction Year: |
2016 |
| Construction Type: |
Facilities |
| District: |
14,
|
|
PROJECT CONTACT: |
| Project Manager: |
Kay Schindel |
| Phone: |
608-266-4668 |
| Email: |
kschindel@cityofmadison.com |
| Inspector: |
Not Available |
| Phone: |
Not Available |
Documents & Specs
|