PUBLIC WORKS CONTRACTS
CONTRACT NUMBER: 7729
CONTRACT: Repaint Madison Water Utility Reservoirs 9, 115, and 315
Percentage of Contract Completed:
Not Available
|
Associated Projects:
- Repaint Madison Water Utility Reservoirs 9, 115, and 315 (86100)
|
PROJECT: |
Repaint Madison Water Utility Reservoirs 9, 115, and 315 |
Project Number: |
86100 |
Bid Due Date: |
06/10/16
|
Bid Open Date: |
06/10/2016 |
Estimated Start Date: |
08/01/2016
|
Estimated Completion Date: |
Not Available
|
Percent of Project Completed: |
Not Available
|
Contract Amount: |
$2,169,600.00
|
Project Contractor: |
Tecorp, Inc.
|
Construction Year: |
2016 |
Construction Type: |
Misc |
District: |
15,
17,
|
PROJECT CONTACT: |
Project Manager: |
Adam Wiederhoeft |
Phone: |
608-266-9121 |
Email: |
awiederhoeft@cityofmadison.com |
Inspector: |
Not Available |
Phone: |
Not Available |